The short answer

Column plumbness and base elevation matter most, because every mechanical package above inherits them. A structure erected out of plumb cannot be corrected once equipment is landed on it.

Structural steel is the datum for everything above it. Deviation here is not absorbed — it is inherited by every mechanical package that follows.

Check the foundation before you lift

Anchor bolt position, projection and base plate elevation should be surveyed and accepted before the first column goes up. Discovering a bolt group is out of position with three columns already standing is an expensive way to learn this.

The measurements that govern

ItemWhy it mattersWhen to check
Base elevationSets every level aboveBefore erection
Column plumbnessEquipment alignment inherits itBefore final bolting
Beam levelGrating and equipment seatingPer level, as erected
Bay dimensionsEquipment will not fit if wrongBefore releasing the bay
Bolt torqueJoint capacityProgressively, recorded

Bolt up in the right order

  • Erect and temporarily bolt, keeping the frame adjustable
  • Plumb and align the bay as a whole, not column by column
  • Only then torque to final value and mark each bolt
  • Record torque on a marked-up drawing as you go

Survey and record

A total station survey per level, recorded and issued, costs very little and settles disputes before they become commercial. It also gives the mechanical team a real datum rather than an assumption.