Skip to content
AARADHYA EPCProjects Pvt. Ltd.

Boilers

CFBC Boiler Erection: The Sequence from Drum Lift to Light-Up

18 April 2026 8 min readBy Aaradhya EPC

The short answer

CFBC erection follows a fixed dependency chain: structure, drum lift, water wall panels, cyclones and loop seal, ducting, refractory, hydro test, then light-up. Refractory curing and cyclone alignment are the two activities that most often govern the critical path.

A circulating fluidised bed boiler is not erected in the order the drawings are numbered. It is erected in the order the dependencies allow, and getting that order wrong is how schedules are lost.

The dependency chain

StageGovernsTypical risk
Structural steelEverything above itFoundation and anchor bolt deviation
Drum liftWater wall hangingCrane availability, weather window
Water wall panelsEnclosure and pressure testPanel damage in transit, fit-up
Cyclones & loop sealGas path completionAlignment, heavy lift access
Ducting & air systemFan commissioningSite fabrication volume
RefractoryLight-upCuring time — cannot be compressed
Hydro testBox-up and insulationRepair joints found late
Light-upHandoverInterlock and E&I readiness

The drum lift is the moment everyone remembers

It is also the one with the most preparation behind it. The lift plan, ground bearing capacity, crane configuration, rigging arrangement and weather window all have to line up on the same day. Water wall panels hang from the drum and top headers, so nothing above the furnace progresses until it is set and levelled.

Practical points

  • Verify anchor bolt positions and elevations before the steel goes up, not after
  • Confirm the crane's ground bearing pressure against the actual made-up pad
  • Set and check drum level before releasing the crane, not the next morning
  • Protect nozzle and manhole faces before any hot work starts nearby

Cyclones: heavy, high, and unforgiving on alignment

The cyclones and loop seal are what make a CFBC a CFBC — solids circulate through them continuously. They are heavy, they sit high, and their alignment with the furnace outlet and return leg has to be right. Misalignment here does not simply look wrong; it affects circulation behaviour once the unit is in service.

Refractory is the activity you cannot compress

Refractory installation and curing follows a defined heat-up curve. That curve is a material property, not a negotiating position. Planners who try to claw back schedule by shortening curing damage the lining and pay for it during the first operating campaign.

Hydro test: find repairs early or pay for them late

The hydro test is a verification, not a discovery exercise. If your NDT coverage and hold-point discipline have been sound, the test confirms what you already know. If they have not, you find out at the worst possible time — after box-up has started, with insulation crews mobilised and waiting.

Light-up and load raising

First firing depends on far more than the boiler: fans, fuel feeding, ash handling, instrumentation, interlocks and the control system all have to be ready together. Mechanical completion is not the same as being ready to light up. Build the punch list closure and E&I interface into the schedule explicitly, or it becomes the invisible tail that adds two weeks.

Topics

CFBC boiler erection sequencecirculating fluidised bed boiler installationboiler drum liftingcyclone erection CFBCrefractory curing boilerboiler hydro test

C-56, Second Floor, Signature Galleria, Near Mahaveer Turning, GIDC Ankleshwar, Bharuch, Gujarat – 393002, India